Purpose
- Improving product CTQ’s (Critical To Quality) metrices
- Sustaining CP/CPK values of more than 1.66
- Enhance customer satisfaction

Project Scope
- Span of project- two main production lines
- Analyze the key production aspects impacting product quality
- Recommend modifications in the process to improve quality parameters

Solution Approach
- Approach based on Six Sigma Methodology: DMAIC (Define, Measure, Define, Measure, Analyze, Improve and Control)
- Statistical analysis of production parameters

The Results
- CP/CPK >1.66 for CTQ’s was achieved within 14 months
- Significant reduction in defect ratios
- Increase in customer orders

Systems, Tools & Services Expertise
- ATS CM4D (Statistical Analysis)