Purpose
- Sludge dewatering by filter presses in three streams and two streams of incineration
- Automation of 10 waste water sites similar to existing automation system back-up
- Increase the processing capacity
Project Scope
- Create Project Documentation (SDS)
- PLC and SCADA Application Development
- Integrated Testing, Factory Acceptance Test (FAT) & Onsite Site Acceptance Test (SAT)
- Onsite commissioning
Solution Approach
- Analysed existing site-back and reverse engineered the automation system
- Utilized knowledge of utility domain & end-client standards for faster project initiation
- Improved processing capacity by replacing automation systems for existing dewatering process, various ancillary plant and equipment
The Results
- Reduced project cost due to hybrid business model
- 100% adherence to project delivery schedules
- 12,000+ hours of engineering supported by a peak time team-size of 25 engineers
Systems, Tools & Services Expertise
- Siemens PCS 7 V7.0